Where Are We Now

This table gives an indication of the project's timetable going forward. The stages have been completed to date in the project can be seen in the Timeline section of the website.

Indicative Headline NWRWTP Timetable

 

Procurement Stage

Target Date

Dialogue and Preparation of Detailed Solutions by Participants

May 2011 to Dec 2011

Clarification of Detailed Solutions

August to Dec 2011

Decision on rail transportation option

March 2012

ISDS De-selection

June 2012

Call for Final Tenders (CFT)

November 2012

Individual authority approved bidder / Final Business Case (FBC) approvals

Late Feb – Early May 2013

Preferred bidder appointed

May 2013

WG approval of FBC

June 2013

Submission of Planning Application

July 2013

Contract Award

August 2013

Planning Consent achieved

Late March 2014

Service commencement

February / March 2017