Where Are We Now
This table gives an indication of the project's timetable going forward. The stages have been completed to date in the project can be seen in the Timeline section of the website.
Indicative Headline NWRWTP Timetable
|
Procurement Stage
|
Target Date
|
|
Dialogue and Preparation of Detailed Solutions by Participants
|
May 2011 to Dec 2011
|
|
Clarification of Detailed Solutions
|
August to Dec 2011
|
|
Decision on rail transportation option
|
March 2012
|
|
ISDS De-selection
|
June 2012
|
|
Call for Final Tenders (CFT)
|
November 2012
|
|
Individual authority approved bidder / Final Business Case (FBC) approvals
|
Late Feb – Early May 2013
|
|
Preferred bidder appointed
|
May 2013
|
|
WG approval of FBC
|
June 2013
|
|
Submission of Planning Application
|
July 2013
|
|
Contract Award
|
August 2013
|
|
Planning Consent achieved
|
Late March 2014
|
|
Service commencement
|
February / March 2017
|
|
|